Cameroon

Engineering, Rehabilitation and Extension of Cameroonian Water Supply Systems (Phase 3 - T3)

(2013-11-01 - 2014-06-30)

The project aims to engineer and rehabilitate water supply systems within the whole country. The contract is divided into 5 phases

 

Limbe

Rehabilitation works including:

  •  - Audit of the water distribution network of the city.
  •  - Design of an HDPE pipe OD 250 – SDR 11, 4.6km.
  •  - Rehabilitation engineering of the ‘Mile II’ water treatment plant (120 m³/h).