Cameroon
Engineering, Rehabilitation and Extension of Cameroonian Water Supply Systems (Phase 5 - T5)
(2016-03-01 - 2017-11-30)
The project aims to engineer and rehabilitate water supply systems within the whole country. The contract is divided into 5 phases
Akonolinga
Rehabilitation works including:
- - Rehabilitation engineering of the intake and the raw water pumping station
- - Rehabilitation engineering of the treatment plant (88 m³/h)
- - Rehabilitation engineering of the treated water pumping station and reinstallation of the hydro-mechanical equipment on the treated water main towards the elevated tank
- - Rehabilitation engineering of the elevated tank
- - Engineering of the electrical line MV/LV
Ambam
Rehabilitation works including:
- - Rehabilitation engineering of the intake and the raw water pumping station
- - Rehabilitation engineering of the treatment plant (22 m³/h)
- - Rehabilitation engineering of the treated water pumping station and reinstallation of the hydro-mechanical equipment on the treated water main towards the elevated tank
- - Rehabilitation engineering of the elevated tank.
Batouri
Rehabilitation works including:
- - Rehabilitation engineering of the intake and the raw water pumping station
- - Rehabilitation engineering of the treatment plant and extension of its capacity (110 m³/h)
- - Rehabilitation engineering of the treated water pumping station and reinstallation of the hydro-mechanical equipment on the treated water main towards the elevated tank
- - Rehabilitation engineering of the elevated tank
Campo
Rehabilitation works including:
- - Rehabilitation engineering of the intake and the raw water pumping station
- - Engineering of a new and more efficient containerized unit (20 m³/h)
- - Engineering of a technical building
- - Rehabilitation engineering of the treated water pumping station
- - Rehabilitation engineering of the elevated tank
- - Reinforcement design of the electrical line MV/LV
Evodoula
Rehabilitation works including:
- - Rehabilitation engineering of the intake and the raw water pumping station
- - Rehabilitation engineering of the treatment plant and extension of its capacity (25 m³/h)
- - Rehabilitation engineering of the treated water pumping station and reinstallation of the hydro-mechanical equipment on the treated water main towards the elevated tank
- - Rehabilitation engineering of the elevated tank
- - Engineering of the electrical line MV/LV
Monatélé
Rehabilitation works including:
- - Rehabilitation engineering of the intake and the raw water pumping station
- - Rehabilitation engineering of the treatment plant (30 m³/h)
- - Rehabilitation engineering of the treated water pumping station and reinstallation of the hydro-mechanical equipment on the treated water main towards the elevated tank
- - Rehabilitation engineering of the elevated tank
- - Reinforcement of the electrical line MV/LV to the treatment plant
Okola
Rehabilitation works including:
- - Rehabilitation engineering of the intake and the raw water pumping station
- - Rehabilitation engineering of the treatment plant and extension of its capacity (25 m³/h)
- - Rehabilitation engineering of the treated water pumping station and reinstallation of the hydro-mechanical equipment on the treated water main towards the elevated tank
- - Rehabilitation engineering of the elevated tank
- - Engineering of the electrical line MV/LV
Sa’a
Rehabilitation works including:
- - Rehabilitation engineering of the intake and the raw water pumping station
- - Rehabilitation engineering of the treatment plant (22 m³/h)
- - Rehabilitation engineering of the treated water pump and reinstallation of the hydro-mechanical equipment’s on the treated water main towards the water storage reservoir
- - Engineering of a new cylindroconical decanter (22m³)
- - Rehabilitation engineering of the reservoir
- - Engineering of the electrical line MV/LV to the treatment plant
Yokadouma
Rehabilitation works including:
- - Rehabilitation engineering of the intake and the raw water pumping station
- - Rehabilitation engineering of the treatment plant and extension of its capacity (80 m³/h)
- - Rehabilitation engineering of the treated water pump and reinstallation of the hydro-mechanical equipment’s on the treated water main towards the water storage reservoir
- - Rehabilitation engineering of the reservoir
- - Engineering of the electrical line MV/LV
Zoétélé
Rehabilitation works including:
- - Rehabilitation engineering of the intake and the raw water pumping station
- - Rehabilitation engineering of the treatment plant (25 m³/h)
- - Rehabilitation engineering of the treated water pumping station and the treated water main towards the elevated tank
- - Rehabilitation engineering of the elevated tank
- - Engineering of the electrical line MV/LV